Hebei Weichang Qixin (300MW) Wind Power Project Fan Foundation Construction Tender Announcement

Hebei Weichang Qixin (300MW) Wind Power Project Fan Foundation Construction Tender Announcement

Bidding number: GDCX02-SGZB16-0424

1.1 Adoption of Domestic Openness, One Step System, Online Bid Opening

1.2 Bidding conditions

The project has been approved by the Development and Reform Commission of the Hebei Provincial Development and Reform Commission for the approval of a new 300MW wind power project in the paddock.

1.3 Project Overview and Bidding Scope

Fan Foundation Construction Project I Section: Model: UP2000 model, numbered QX1-QX33, a total of 33 bases;

Fan Foundation Construction Project II Lot: Model: UP2000 model, numbered QX41~QX45, QX49~QX78, total 35 bases;

Fan Foundation Construction Project III tender section: Model: UP2000 model, numbered as QX34 ~ QX40, QX46 ~ QX48, QX79 ~ QX93, QX138 ~ QX150, a total of 38 bases;

Fan Foundation Construction Project IV tender section: Model: UP2000 model, numbered QX109~QX117, QX127~QX137, total 20 bases;

Fan Foundation Construction Project V Lot: Model: UP2000 model, numbered QX94~QX108, QX118~QX126, total 24 bases.

The main work includes: basic construction of fan foundation and box change, grounding of wind turbines and box transformers (materials provided by grounding units), unloading, inspection, on-site storage and installation of foundation rings, and fabrication and installation of other embedded parts (such as Cable embedded pipe, foundation ring support), basic anti-corrosion and waterproof. Fan foundation backfill lifting platform compaction flat (50m × 40m), laying gravel surface, the outer ring of the base ring reinforced plastic rubber strip adhesive installation, installation of settlement observation point device buried. Part of the construction of temporary roads, the recovery of basic platforms and temporary land occupation.

1.4 Bidder qualification requirements

No.

Section name

Bidder’s financial, qualification and performance requirements

1

Fan Foundation Construction Project Bid 1

1. Qualifications of legal persons: An independent enterprise legal person registered in the territory of the People's Republic of China

2. Qualification requirements: Qualification of the general contractor for construction project construction or “ink” style="word-break: break-all; padding: 0px 3px;"> Qualification of construction contractor

3. Project performance: Project performance: In the past 5 years, the wind turbine foundation construction with a single turbine capacity of 1.5MW and above has been completed. Three projects or more or nearly five years have completed a cumulative total of 50 turbines with a single turbine capacity of 1.5MW and above. Need to attach contract documents

4. Personnel requirements: The project manager must have a production safety assessment certificate (Class B) and registered secondary architect qualifications, and have a fan foundation construction project performance

5. Financial ability: good operating conditions

6. Integrity performance: Good business reputation, no bad record of project quality, no delay in the duration of the project; In the process of signing the contract and fulfilling the contract in the past three years, there is no record of integrity.

7. Constraints: The company has not been ordered to suspend business, the property has been taken over, frozen, or bankruptcy; the person in charge of the unit is the same person or two or more units that have a controlling and controlled relationship and may not bid in the same tendering project, otherwise All waste label processing

8, Commonwealth bid: Do not accept the Commonwealth bid

9. There are more divisions in this target segment, and the same bidder can only bid up to two of the bid segments. If the bidder has more than two bid segments ranked first in the overall bid evaluation, then the bid winner will be determined according to the principle favorable to the tenderee. Lots, and in turn determine the winning bids for the remaining bids

2

Fan Foundation Construction Project Bid 2

1. Qualifications of legal persons: An independent enterprise legal person registered in the territory of the People's Republic of China

2. Qualification requirements: Qualification of general contracting for construction project construction or Qualification of general contracting for construction and construction

3. Project performance: In the past 5 years, the wind turbine foundation construction performance with a single turbine capacity of 1.5MW and above has been completed. Three projects or more or nearly five years have completed a cumulative total of 50 turbines with a single turbine capacity of 1.5MW and above. certified documents

4. Personnel requirements: The project manager must have a production safety assessment certificate (Class B) and registered secondary architect qualifications, and have a fan foundation construction project performance

5. Financial ability: good operating conditions

6. Integrity performance: Good business reputation, no bad record of project quality, no delay in the duration of the project, and in the process of signing the contract and fulfilling the contract in the past three years, there is no record of integrity.

7. Constraints: The company has not been ordered to suspend business, the property has been taken over, frozen, or bankruptcy; the person in charge of the unit is the same person or two or more units that have a controlling and controlled relationship and may not bid in the same tendering project, otherwise All waste label processing

8, Commonwealth bid: Do not accept the Commonwealth bid

9. There are more divisions in this target segment, and the same bidder can only bid up to two of the bid segments. If the bidder has more than two bid segments ranked first in the overall bid evaluation, then the bid winner will be determined according to the principle favorable to the tenderee. Lots, and in turn determine the winning bids for the remaining bids

3

Fan Foundation Construction Project Bid 3

1. Qualifications of legal persons: An independent enterprise legal person registered in the territory of the People's Republic of China

2. Qualification requirements: Qualification of general contracting for construction project construction or Qualification of general contracting for construction and construction

3. Project performance: In the past 5 years, the wind turbine foundation construction performance with a single turbine capacity of 1.5MW and above has been completed. Three projects or more or nearly five years have completed a cumulative total of 50 turbines with a single turbine capacity of 1.5MW and above. certified documents

4. Personnel requirements: The project manager must have a production safety assessment certificate (Class B) and registered secondary architect qualifications, and have a fan foundation construction project performance

5. Financial ability: good operating conditions

6. Integrity performance: Good business reputation, no bad record of project quality, no delay in the duration of the project, and in the process of signing the contract and fulfilling the contract in the past three years, there is no record of integrity.

7. Constraints: The company has not been ordered to suspend business, the property has been taken over, frozen, or bankruptcy; the person in charge of the unit is the same person or two or more units that have a controlling and controlled relationship and may not bid in the same tendering project, otherwise All waste label processing

8, Commonwealth bid: Do not accept the Commonwealth bid

9. There are more divisions in this target segment, and the same bidder can only bid up to two of the bid segments. If the bidder has more than two bid segments ranked first in the overall bid evaluation, then the bid winner will be determined according to the principle favorable to the tenderee. Lots, and in turn determine the winning bids for the remaining bids

4

Fan Foundation Construction Project Bid 4

1. Qualifications of legal persons: An independent enterprise legal person registered in the territory of the People's Republic of China

2. Qualification requirements: Qualification of general contracting for construction project construction or Qualification of general contracting for construction and construction

3. Project performance: In the past 5 years, the wind turbine foundation construction performance with a single turbine capacity of 1.5MW and above has been completed. Three projects or more or nearly five years have completed a cumulative total of 50 turbines with a single turbine capacity of 1.5MW and above. certified documents

4. Personnel requirements: The project manager must have a production safety assessment certificate (Class B) and registered secondary architect qualifications, and have a fan foundation construction project performance

5. Financial ability: good operating conditions

6. Integrity performance: Good business reputation, no bad record of project quality, no delay in the duration of the project, and in the process of signing the contract and fulfilling the contract in the past three years, there is no record of integrity.

7. Constraints: The company has not been ordered to suspend business, the property has been taken over, frozen, or bankruptcy; the person in charge of the unit is the same person or two or more units that have a controlling and controlled relationship and may not bid in the same tendering project, otherwise All waste label processing

8, Commonwealth bid: Do not accept the Commonwealth bid

9. There are more divisions in this target segment, and the same bidder can only bid up to two of the bid segments. If the bidder has more than two bid segments ranked first in the overall bid evaluation, then the bid winner will be determined according to the principle favorable to the tenderee. Lots, and in turn determine the winning bids for the remaining bids

5

Fan Foundation Construction Project Lot 5

1. Qualifications of legal persons: An independent enterprise legal person registered in the territory of the People's Republic of China

2. Qualification requirements: Qualification of general contracting for construction project construction or Qualification of general contracting for construction and construction

3. Project performance: In the past 5 years, the wind turbine foundation construction performance with a single turbine capacity of 1.5MW and above has been completed. Three projects or more or nearly five years have completed a cumulative total of 50 turbines with a single turbine capacity of 1.5MW and above. certified documents

4. Personnel requirements: The project manager must have a production safety assessment certificate (Class B) and registered secondary architect qualifications, and have a fan foundation construction project performance

5. Financial ability: good operating conditions

6. Integrity performance: Good business reputation, no bad record of project quality, no delay in the duration of the project, and in the process of signing the contract and fulfilling the contract in the past three years, there is no record of integrity.

7. Constraints: The company has not been ordered to suspend business, the property has been taken over, frozen, or bankruptcy; the person in charge of the unit is the same person or two or more units that have a controlling and controlled relationship and may not bid in the same tendering project, otherwise All waste label processing

8, Commonwealth bid: Do not accept the Commonwealth bid

9. There are more divisions in this target segment, and the same bidder can only bid up to two of the bid segments. If the bidder has more than two bid segments ranked first in the overall bid evaluation, then the bid winner will be determined according to the principle favorable to the tenderee. Lots, and in turn determine the winning bids for the remaining bids

1.5 Potential bidders wishing to purchase tender documents should first be members. For registered members, please contact customer service department.

1.6 Selling Bidding Documents:

The tender documents are purchased using the online payment model (wireless transfer, online banking transfer, on-site cash payment and other purchase methods are not accepted). The system also supports corporate online banking payment and personal online banking payment.

1.6.1 If purchased through a company account, company accounts must have online banking capabilities. When online payment is made, this website will be redirected (linked) to the bank website selected by the purchaser.

1.6.2 If purchased through a personal account, it will be considered that the purchaser has obtained authorization from the company and is equivalent to a company purchase. Before you purchase, verify that the online payment limit of your bank card is not less than the selling price of the bidding documents, so as not to affect the purchase of the bidding documents.

1.6.3 The bidder must be the bidder. The basic information such as bidder's name, correspondence address, contact person, and contact information that the potential bidder fills in on the platform must be accurate, and the information on the whole process of tendering and bidding should be issued and contacted.

1.6.4 After successful payment, bidders directly download the electronic version of the bidding documents from the Internet. The tenderer/bidding agency does not provide any paper tender documents. Successful payment means that the tender documents have been sold. Except for the reasons of the tenderer or the bidding agency, the tender documents will not be refunded once sold.

1.6.5 The bidding agency will mail the commercial invoice for the bidding documents to potential bidders as soon as possible according to the mailing address filled in when purchasing the bidding documents.

1.6.6 If the bidding document fails to be purchased or other problems, please contact customer service center.

1.7 Date of Sale of Bidding Documents: The tender documents will be sold from 09:00 on November 15, 2016 to 16:00 on November 22, 2016.

1.8 Price of Bidding Documents and Bid Security

No.

project name

Quantity

Tender Document Price (yuan)

Duration

Tender number

Bid security (yuan)

1

Fan Foundation Construction Project Bid 1

3000 yuan

The project was started on April 1, 2017 and completed on September 20, 2017 (including the preparation of raw materials and the foundation of the mixing plant in 2016, and the main body pouring time was May 20 to August 20, 2017).

GDCX02-SGZB16-0424/01

505,000 yuan

2

Fan Foundation Construction Project Bid 2

3000 yuan

The project was started on April 1, 2017 and completed on September 20, 2017 (including the preparation of raw materials and the foundation of the mixing plant in 2016, and the main body pouring time was May 20 to August 20, 2017).

GDCX02-SGZB16-0424/02

495,000 yuan

3

Fan Foundation Construction Project Bid 3

3000 yuan

The project was started on April 1, 2017 and completed on September 20, 2017 (including the preparation of raw materials and the foundation of the mixing plant in 2016, and the main body pouring time was May 20 to August 20, 2017).

GDCX02-SGZB16-0424/03

555,000 yuan

4

Fan Foundation Construction Project Bid 4

3000 yuan

The project was started on April 1, 2017 and completed on August 20, 2017 (including the preparation of raw materials and the foundation of the mixing plant in 2016. The basic casting time for the main body was May 20 to July 20, 2017).

GDCX02-SGZB16-0424/04

405,000 yuan

5

Fan Foundation Construction Project Lot 5

2000 dollars

The project was started on April 1, 2017 and completed on August 20, 2017 (including the preparation of raw materials and the foundation of the mixing plant in 2016. The basic casting time for the main body was May 20 to July 20, 2017).

GDCX02-SGZB16-0424/05

305,000 yuan

1.9 Deadline of tender documents: At 11:00 (Beijing time) on December 06, 2016, overdue or non-conforming tender documents are not accepted.

Contact: Qian Yong

Mobile:

phone

fax

E-mail:

In order to ensure that you can bid smoothly, please consult the bidding agency or the tenderer for detailed requirements for bidding before bidding or purchasing the bidding documents. The specific requirements and project conditions shall be interpreted by the bidding agency or the tenderee.